Many homeowners are left wondering how long a full bathroom renovation will take. They may have a general idea but are not sure of all the specifics that go into it. It can lead to frustration and impatience as they wait for almost an eternity for their new bathroom renovation to finish.
As a homeowner who invested in your property, you should know how long a renovation will last to help you prepare for it and know what to expect.
This article will cover everything to know about a full bathroom renovation timeline.
How Long Do All the Full Bathroom Renovation Jobs Take?
A full bathroom renovation consists of various jobs. Each has its timeline and can take anywhere from one day to several weeks.
The following is the rough estimation of the time needed for each task to get done during a full bathroom renovation:
Demolition
If you demolish the old fixtures, it will take only a few hours. But if you’re tearing down the wall studs and removing the tiles, it can take up to five days.
If you’re demolishing a bathroom with brick walls, it will take significantly longer, as bricks are much harder to break down. Expect the demolition process to take anywhere from five to seven days.
Plumbing
The plumbing portion of a bathroom renovation can be one of the more time-consuming aspects. It can take up to more than three days, depending on the work needed.
If you’re moving plumbing fixtures around, it will take even longer. It can add a week or two to the timeline.
Electrical
The electrical portion of a bathroom renovation is usually pretty straightforward and won’t take more than a few days. But if you’re moving light fixtures or outlets around, it can take longer.
Waterproofing and Painting
If you’re only painting, it will usually take only a day. But removing and installing new drywall can take up to three days.
Tile Installation
Tiling can be easy, but it takes a lot of time. Tiling includes prepping and levelling walls and floors before laying out the tiles and drying time before they can be used.
If done by a professional whose only job is to lay tiles, it can last up to a week, but if the tiler has other work, tiling can last for more than two weeks. If you DIY, it can take longer.
Fixture Installation
The fixture installation portion of a bathroom renovation is usually pretty quick and shouldn’t take more than a day or two.
What will take most of the time is if you have to wait for other works, such as the electrical and plumbing. If those are completed beforehand, the installation of tiles, fixtures, and other finishing touches will go much more smoothly and quickly.
Summary of the Timeline for Each Renovation Job
- Demolition: few hours to seven days
- Plumbing: few hours to two weeks
- Electrical: few hours to three days
- Painting: one day
- Drywall removal and installation: three days
- Tile installation: one to two weeks
- Fixture installation: few hours to one day
Other Factors Affecting the Length of Time for a Bathroom Renovation
Source of materials
If you’re getting your materials from a specialty store, expect the renovation to take longer, as the materials need to be customised. It can add an extra week or two to the timeline.
If you’re getting your materials from a general hardware store, the renovation will go much quicker, as the materials won’t need to be customised.
Where the materials are coming from is also a consideration. If imported, the delivery time can take longer.
DIY jobs
If you’re doing the renovation yourself, it will likely take longer than if you’re hiring a professional. It is because professionals have experience completing these jobs quickly and efficiently, although DIYing can save you money.
Acquiring permits
Getting permits takes around two weeks or more. Inspections are also needed, placing you on a waiting list that may last from days to weeks.
Frequently Asked Questions
Can you remodel a bathroom in two days?
If you’re the only client, bathroom remodelling can be as short as one to two days, depending on the work needed. It can take more than two days if intense plumbing or electrical work is necessary, such as relocation of the tub or electrical layout.
How long does it take to change a bathroom?
A full bathroom renovation for a small bathroom can take less than a month or more than 20 days if builders are required to work on weekends. If not, it can take between 1-2 months.
How long does it take to tile a bathroom?
If you’re getting your materials customised, the renovation will take longer, as the materials will need to be made specifically for your bathroom. It can add an extra week or two to the timeline.
How do you survive a bathroom renovation?
Know the starting schedule of the renovation project. Move everything out of the bathroom two days before.
Create a space to be a temporary bathroom, which may need a vanity, face washing area, and other essentials to do your private business.
If you don’t know how to create a make-shift bathroom or your contractor doesn’t provide it, ask for help from neighbours and friends beforehand.
How long does it take to redo a small bathroom?
It depends on how much work is needed or if any unexpected accidents or situations happen. It can be as short as days, two months or more.
Summary
How long a full bathroom renovation takes depends on the project’s complexity. But the process usually includes demolition, plumbing and electrical work, tile installation, and fixture installation. If you’re DIYing the renovation, you can save money but not time.
Permits may take some time to acquire, and inspections may be required.